CPC vows more consultation with other parties  • Fighting between DR Congo army, ADF rebels leaves 39 dead  • Israel successfully tests Arrow 3 ballistic missile interceptor  • Gold price closes down in Hong Kong  • China auto sales hit monthly record high  • Foreign exchange rates in India  • Senior CPC official meets U.S. think tank representatives  • Zuma's removal of finance minister shocks nation  • Sri Lanka to sign international convention to protect citizens from enforced disappearances  • Singapore stocks close 0.44 pct lower  
You are here:   Home

China audit finds slow progress on Beijing's new airport project

Xinhua, December 10, 2015 Adjust font size:

The construction of Beijing's new airport is behind schedule due to lagging land requisition and demolition work, the country's top auditing authority said on Thursday.

By the end of October, Beijing and Hebei province delivered less than half of the total land needed, with 16.7 million out of all 27.3 million square meters of land still required, according to a report from the National Audit Office.

The new airport, which was authorized for construction by the State Council in December 2012 and is considered a key step for the coordinated development of the Beijing-Tianjin-Hebei region, is expected to be finished by 2019.

Meanwhile, the report showed that many other major construction projects were also behind schedule with 12 railway projects barely achieving 10 percent of their annual plans which involve 8.57 billion yuan (1.33 billion U.S. dollars) of planned investment. Endi