News Analysis: Fuel scarcity bites harder in Nigeria  • 192 Bangladeshi students to get Chinese gov't scholarship this year  • China Hushen 300 index futures close lower Thursday  • China treasury bond futures close lower Thursday  • Spotlight: Dutch referendum says "No" to EU-Ukraine deal  • 2 wounded in rocket fire from Syrian side  • Xinjiang investing heavily in infrastructure in 2016  • Australian consumer anxiety at three year low  • Roundup: Nguyen Xuan Phuc elected Vietnamese Prime Minister  • Tokyo stocks reverse losses to end higher on gov't vows to curb yen rise  
You are here:   Home

WB finances Bangladesh 217 mln USD to upgrade power station

Xinhua, April 7, 2016 Adjust font size:

The Bangladeshi government Thursday signed a 217 million U.S. dollars financing agreement with the World Bank's International Development Association (IDA) to upgrade a unit in a power station, which will increase the unit's existing electricity generation capacity by more than double.

The agreement was signed by Kazi Shofiqul Azam of Bangladesh's Economic Relations Division and Rajashree Paralkar of the World Bank on behalf of their respective sides in Dhaka.

The Washington-based lender said the Ghorashal Unit 4 Repowering Project will transform a gas-fired steam unit that is currently generating 170 MW into an energy efficient 409 MW plant.

Such conversion to combined cycle technology will increase the plant's overall efficiency from existing 30 percent to 54 percent while requiring only 18 percent more natural gas, it said.

"Bangladesh can grow its economy much faster and reduce poverty significantly if its energy infrastructure can meet the demand for reliable, low-cost electricity," said Rajashree Paralkar, World Bank Acting Country Director for Bangladesh.

"The project will increase the efficiency in gas utilization of an existing unit, while adding new generation capacity to address the country's severe power needs."

The project will also reduce the specific fuel consumption per gigawatt hour by 44 percent and lower greenhouse gas emissions, said the bank. In addition, it said the project will provide capacity building and institutional support to the Bangladesh Power Development Board.

"The government has prioritized improving the efficiency of gas-based power plants, given the shortages in natural gas production," said Kazi Shofiqul Azam, Additional Secretary, Economic Relations Division, government of Bangladesh.

"The repowering of the Ghorashal Unit 4 will quickly add new generation capacity without adding major infrastructure costs for fuel supply." Endit