1st LD Writethru: U.S. stocks bounce back as Fed meeting begins  • Nigeria leaves 2016 CHAN after losing 1-0 to Guinea  • Chinese envoy calls for reactivating peace process between Palestine and Israel  • Roundup: Forum in Norway calls for responsible development of the Arctic  • Kremlin refutes U.S. official accusations against Putin  • Mint gold sales in Austria up 45 pct year-on-year in 2015  • 1st LD Writethru: U.S. dollar dips ahead of Fed statement  • UN health agency mobilizes teams to help countries combat Zika virus  • Urgent: U.S. stocks bounce back as Fed meeting begins  • Migrant, refugee sea arrivals in Greece surpass 45,000 this year: IOM  
You are here:   Home

Rio Olympic Park hits 97% completion

Xinhua, January 27, 2016 Adjust font size:

Construction work at Rio de Janeiro's Barra Olympic Park, the main venue cluster for this year's Olympic Games, has hit 97% completion, organizers said on Tuesday.

The complex, which will will host 16 of the 42 Olympic sports and nine of the 23 Paralympic disciplines, was 95% finished in December.

Meanwhile the velodrome, which will host the track cycling test event from April 29 to May 1, is 80% ready, up from 76% in December.

At Deodoro Park, the second largest venue cluster, Youth Arena has made the fastest progress, reaching 80% completion compared with 75% in December.

The venue will host basketball, fencing and wheelchair fencing.

Carioca Arena 1 and the Olympic hockey center are 100% complete and have already staged successful test events. Endit